Community Impact

Explore how the proposed bond could affect the community

See the needs identified across the district, the projects being considered, how they may affect the community, and the official information behind each proposal.

How the proposal reaches the community

Keller ISD has not released a category-level dollar breakdown of the $828.1M called bond package beyond the five proposition totals. To avoid implying allocations that have not been published, the visualizations below use verified scope indicators — not dollar splits.

Proposed program areas — verified scope

Board Approved · July 23, 2026

Campuses and community reach

34 campuses & facilities

Districtwide maintenance and technology reach all campuses. Bars show the count of campuses in each category — not a per-campus funding amount.

Elementary / middle / high counts reflect Keller ISD's published campus roster. Confirm final counts against the district directory.

Program area status

Information Confidence Framework

All four program areas were approved by the Board of Trustees on July 23, 2026. Ballot placement, funding, and construction remain pending later official milestones.

  • Districtwide Maintenance Board Approved
  • Keller Middle School Board Approved
  • Technology Board Approved
  • Athletics & Shared Facilities Board Approved
Have a question about a program area?

Ask CivicCentra IQ about scope, sources, or what remains pending.

Ask a question →
Official — Board Approved, July 23, 2026Dollar-level allocation: Not yet released

Community Impact figures summarize currently available official project and funding information. Project scope, costs, schedules, and allocations may change through board review, design, procurement, and implementation. Official records remain the authoritative source.

Current Condition
  • The CBAC reviewed facility issues across the district as part of an approximately $1.3 billion facility-needs analysis.
Proposed Investment
  • Maintenance repairs and renovations at 34 campuses and facilities.
Potential Community Relevance
  • Could extend the useful life of existing buildings
  • Could reduce emergency repair demands
  • Could improve reliability of HVAC, plumbing, electrical, roofing, and life-safety systems
  • Could reduce pressure on operating funds currently used for major repairs

Informational — not guaranteed outcomes.